Planning Application Process
- 1
Application Submitted
Development Support Services receives the application package.
- 2
Completeness Check
Planner reviews the application to confirm required information has been provided.
- 3
Initial Planner Review
Planner reviews the application for compliance and identifies any initial deficiencies/ risks to approval. Planner holds initial review meeting with applicant at this time.
- 4
Applicant Review / Acceptance
Applicant reviews the comments, addresses required items and confirms direction to proceed.
- 5
Circulation
The application is circulated for internal and external review and comment.
- 6
Comments Review
Planner reviews circulation comments and identifies whether additional information or revisions are required.
- 7
Applicant Response
If deficiencies are identified, the applicant provides the required information before the application proceeds.
- 8
Internal Review
Planner completes internal review and prepares the application to move forward to decision. (If outstanding items exist, return to Step 7.)
- 9
Planner Report
Planner prepares the report and recommendation.
- 10
Decision
Planner prepares administrative report and recommendation for decision-making authority’s consideration.