Division
7
Capital Project type
Drainage
Overview
Diversion of stormwater runoff from the upstream catchment area of Langdon along Glenmore Trail towards Weed Lake, reducing the potential flooding within the Hamlet of Langdon.
Phase 1 Design
Q3 2025
Phase 2 Tender
Q3 2025
Phase 3 Construction
Q2 2026
Timeline Items