On November 17, 2026, the Alberta Utilities Commission (AUC) approved the Indus Thermal Power Plant application, which is a 1,494 megawatt (MW) power plant to support the Beacon AI Data Centre.
The County participated in the hearing and provided input to the AUC regarding the County’s planning framework and the zoning regulations that are in place on the subject site.
In its decision, the AUC approved the power plant, with some conditions. You can read the AUC’s full decision here, including its findings on the matters of noise, water, environment, and air quality impacts.
What happens next?
Before the project can proceed with development, the proponent will require a development permit approval from Rocky View County. While the County is required to grant development approval that aligns with the AUC’s decision, the AUC noted in its decision that the County retains the authority to manage the following matters through its development permit process:
- landscaping
- weed control
- project screening and fencing
- municipal reclamation security under the S-DAT district
- lighting
- road access and parking
- construction and traffic management plan
- stormwater
- surface water management and wastewater discharge
- visual mitigation
- an updated agrivoltaics plan (this is required by the Beacon ASP)
The County is currently reviewing the AUC decision and the implications for the development permit process.
Background
On June 17, 2025, Rocky View County Council approved the Beacon AI Hub Area Structure Plan (ASP) to guide a proposed data centre development on approximately 900 acres near Indus, Alberta, and redesignated the lands to a Special, Data Centre (S-DAT) land use district. The ASP states that power for the data centre is expected to be provided by the electrical grid.
The approved ASP can be viewed here: Beacon AI Hub Area Structure Plan [PDF/6.4MB].
In September 2025, the Province restricted new electricity-grid connections for data centres and required that data centres must provide their own power. The proponent of the Beacon AI Data Centre subsequently applied to the Alberta Utilities Commission (AUC) to construct an on-site natural gas-fired power plant to supply the proposed data centre.
On January 19, 2026, the AUC publicly posted a Notice of Application for the proposed power plant. This notice informed residents and interested parties about the proposal and opened a window for public feedback.
On February 10, 2026, Rocky View County Council directed Administration to formally participate in the AUC's review process. The AUC held a hearing for the application in August 2026 and released its decision on November 17, 2026.
Separate from the Beacon ASP, the County began an Emerging Sector Strategy project in December 2025 to investigate the impacts of data centres and create a comprehensive planning framework to regulate them. That project is still underway, and you can find more information about it here: Data Centres and the Emerging Sector Strategy | Your View