Anticipated Traffic Impacts, Eastbound Highway 8 to Northbound Westbound Stoney Trail Closure
Starting this week, if weather conditions allow, the contractor is preparing to complete
ongoing tie-in work between the newly aligned eastbound lanes and existing infrastructure.
Please note that if this work cannot move forward due to weather conditions, work will occur
in the new year.
This work is entirely weather dependent. If conditions allow for the work to proceed, access
to northbound Stoney Trail will be closed for eastbound traffic on Highway 8 to northbound
Stoney Trail.
This closure is required to provide space for workers to remove the existing construction
detour and complete the tie-in between Highway 8 and Stoney Trail. Traffic signage will
be present, and an alternate route will be communicated through onsite signage when the
Alternate Route
Access to northbound Stoney Trail for eastbound Highway 8 traffic will be provided via the
69th Street interchange. See map below for details.
https://www.alberta.ca/highway-8-improvements-eastbound-elbow-river-briā¦