Langdon Servicing - Technical Review Committee

Contents


Latest News

In May 20, 2025 Council approved an Terms of Reference for the Langdon Servicing – Technical Review Committee project. The scope of the project to determine the efficient expansion of servicing/infrastructure for the study area indicated in the map below:


Map of the study area for Langdon Servicing - TRC project

As part of the first phase of this project, Langdon Waterworks will be commissioning four technical studies for the study area, which pertains to the following utility/servicing infrastructure: potable water, sanitary sewer, transportation, and storm water systems. Langdon Waterworks will be responsible for keeping the representatives up to date on progress or findings of the studies.

In Phase 1 of the project, a Technical Review Committee will be established, where they will review and make recommendations to support the expansion of the servicing infrastructure.  An Infrastructure Assessment Report will be produced as part of the deliverables in Phase 1 of the project.

Council will appoint the members prior to the first meeting of the Technical Review Committee. The Technical Review Committee will be dissolved once the Infrastructure Assessment Report is presented and accepted by Council. Following the conclusion of the Phase 1, this Infrastructure Assessment Report will inform the subsequent phases of an amendment to the Langdon ASP, which will be carried out by the County.

The Technical Review Committee will be composed of the following organizations:

  • Langdon Waterworks – 2 representatives
  • Ducks Unlimited – 1 representative
  • Western Irrigation District (WID) – 1 representative
  • Rocky View County – 2 representatives
  • General Public – 2 members

Next Steps

CALL OUT FOR MEMBERS!

Are you a resident, or own a property in the hamlet of Langdon, or within the lands in the study area?

Rocky View County is seeking members for the Langdon Servicing – Technical Review Committee. Please see the attached notice here for more information about the TRC.

To Apply:

Please submit a brief expression of interest including:

  • Your name and contact information
  • A short statement (max 300 words) describing your interest in serving on the TRC, any relevant background, and what you hope to contribute

Applications can be sent to planning_policy@rockyview.ca. The deadline to apply to be on the Technical Review Committee will be on June 25, 2025.


Background

The Langdon plan area is positioned along Centre Street and extends approximately one mile east and west from Centre Street, encompassing approximately 15 quarter sections for a total of 947 hectares (2,340 acres). Langdon offers a variety of amenities and services for its nearly 5,000 residents including schools, open space, local shops, businesses, and recreational uses.

The County adopted the first ASP for Langdon in April 1999 to respond to the growth pressures facing the community, which were also subsequently amended in 2009 and 2013. In 2014, the County prepared a new ASP to replace the Langdon ASP to consider boundary expansion and ensure compliance with the Municipal Development Plan (the County Plan). This ASP amendment was approved in 2016 and added approximately 950 acres of land to Langdon and established a future study area for lands that could be considered for future expansion.

On November 28, 2023, Council approved the Terms of Reference for a developer-led and developer-funded Langdon ASP amendment to include an additional four quarter sections into the hamlet boundary. Currently, this project is ongoing but is separate from the scope of this Langdon Servicing – Technical Review Committee project.


Project Timeline

The Plan will be prepared in four phases:

Phase 1 - Project Initiation
  • Establishment of the Langdon Servicing – Technical Review Committee
  • Initiation of Technical Servicing Studies
  • Implementation of Engagement Strategy with landowners in the study area
  • Infrastructure Report
Q2, 2025
Phase 2 - Community Visioning
  • Establishment of a Visioning Committee
  • Public Engagement*
  • Committee Report
Q3, 2025
Phase 3Draft ASP Amendment
  • Draft policy/map amendments based on Infrastructure Report
  • Land Use Strategy
  • Circulation/Public Review
Q4, 2025
Phase 4 - Bylaw Adoption
  • Public Hearing
Q1, 2026

*Timelines are estimated and subject to change


Related Information

The Langdon Servicing – Technical Review Committee project will align with other statutory plans, policies, and studies that have been adopted since the original Area Structure Plan was completed in 1999.

Please visit the links below to review these related documents:


Get Involved

To learn more about the first phase of this project, please contact:

Alan Boucher RPP, MCIP - Principal 
BLV Development Management
blvinc23@outlook.com | 403-470-8108

You can also contact us at planning_policy@rockyview.ca or 403.230.1401 for questions related to this project.





           


FOIP Notification: Personal information provided through this online form is collected in accordance with section 33(c) of the Alberta Freedom of Information and Protection of Privacy Act. The information is collected for the purpose of creating and maintaining a mailing list to provide interested parties updates on the status of this project. Questions about the collection, use, and disclosure of this information can be directed to the Manager of Planning & Development Services at 403-230-1401.

Contact

Planning Policy
403-520-8158
Planning_Policy@rockyview.ca

County Plans Overview

Check out the County Plans Overview (PDF) for a quick look at the different types of planning documents used in the County and how they interact.