Bridge File 78180 Replacement

Overview

Bridge File 78180 carries Rge Rd 273 over the Western Irrigation District Canal, north of Twp Rd 230. The existing structure is a 21 metre, 3 span concrete girder bridge, which was built in 1977 and has reached the end of its service life.

Project Timeline

Engineering and construction are planned for 2024. Construction anticipated November 2024 – February 2025. To be confirmed once a contract has been awarded. Construction must take place outside of the WID operating window of April to October.

Should you have any questions or require additional information, please contact Eric Schuh, Project Manager at 403-230-1401, or eschuh@rockyview.ca.

Contact

Capital Projects
T: 403.230.1401
F: 403.277.3113
capitalprojects@rockyview.ca