Bragg Creek Transfer Site – Erosion Management Project

Overview

The Bragg Creek Transfer Site is an active waste and recycling transfer site. In 2020, concerns for site erosion and ongoing site maintenance were reviewed, and action items identified. A staged approach has been applied to the project, to maintain services on the site and provide the upgrades in priority. Work began in the summer of 2021 and all upgrades are anticipated to be completed by the fall of 2023.

The overall scope of the work includes the installation of catch basins and drainage ditches to mitigate site erosion and increase site drainage. Asphalt paving of the user area to increase user ease and access, and to reduce future maintenance costs. Minor grading to increase onsite storage and stabilization of the slope along the east boundary of the user area.

Project Timeline

  • Phase 1
    Fall 2021
    Drainage Improvements, Concrete and Asphalt Paving
  • Phase 2
    Fall 2022
    Site Grading, Concrete and Asphalt Paving
  • Phase 3
    Fall 2023
    Site Grading, Concrete and Asphalt Paving
  • Update: Final slope grading and landscaping to be completed in Spring 2024

Should you have any questions or require additional information, please contact Stephanie Collinson, Project Manager at 403-230-1401, or via email at scollinson@rockyview.ca.